An aggregate is said to be flaky, if its least dimension is less than

An aggregate is said to be flaky, if its least dimension is less than
  • A.  3/4 mean dimension
  • B.  2/3 mean dimension
  • C.  3/5 mean dimension
  • D.  5/8 mean dimension
  • Correct Answer: Option A

The maximum thickness of concrete floor of a cement warehouse, is

The maximum thickness of concrete floor of a cement warehouse, is
  • A.  25 cm
  • B.  15 cm
  • C.  10 cm
  • D.  20 cm
  • Correct Answer: Option A

For an ordinary Portland cement

For an ordinary Portland cement
  • A.  soundness varies from 5 to 10 mm
  • B.  residual does not exceed 10% when sieved through IS Sieve No. 9
  • C.  initial setting time is not less than 30 minutes
  • D.  compressive stress after 7 days, is not less than 175 kg/cm
  • Correct Answer: Option C

For compacting plain concrete road surface of thickness less than 20 cm, we use

For compacting plain concrete road surface of thickness less than 20 cm, we use
  • A.  screed vibrator
  • B.  internal vibrator
  • C.  form vibrator
  • D.  none of these.
  • Correct Answer: Option A

The light weight aggregates are obtained from

The light weight aggregates are obtained from
  • A.  metamorphic rocks
  • B.  igneous rocks
  • C.  volcanic source.
  • D.  sedimentary rocks
  • Correct Answer: Option C

The process of hardening the concrete by keeping its surface moist is known

The process of hardening the concrete by keeping its surface moist is known
  • A.  compacting
  • B.  curing
  • C.  placing
  • D.  wetting
  • Correct Answer: Option B

The final operation of finishing floors, is known as

The final operation of finishing floors, is known as
  • A.  screeding
  • B.  floating
  • C.  finishing
  • D.  trowelling
  • Correct Answer: Option D

A construction joint is provided where

A construction joint is provided where
  • A.  bending moment is small
  • B.  shear force is small
  • C.  all
  • D.  the member is supported by other member
  • Correct Answer: Option C

Workability of concrete for a given water content is good if the aggregates, are

Workability of concrete for a given water content is good if the aggregates, are
  • A.  irregular aggregate
  • B.  rounded aggregate
  • C.  angular aggregate
  • D.  flaky aggregates.
  • Correct Answer: Option B

C.R.R.I. charts are used to obtain a relatioship between strength of concrete and

C.R.R.I. charts are used to obtain a relatioship between strength of concrete and
  • A.  fineness modulus
  • B.  grading of aggregate
  • C.  workability
  • D.  water cement ratio
  • Correct Answer: Option D

The grade of concrete not recommended by I.S. : 456, is

The grade of concrete not recommended by I.S. : 456, is
  • A.  M 300
  • B.  M 500
  • C.  M 200
  • D.  M 400
  • Correct Answer: Option B

The compaction of concrete, improves

The compaction of concrete, improves
  • A.  durability
  • B.  density
  • C.  all
  • D.  strength
  • Correct Answer: Option C

The internal dimensions of a ware house are 15 m x 5.6 m, and the maximum height of piles is 2.70 m, the maximum number of bags to be stored in two piles, are

The internal dimensions of a ware house are 15 m x 5.6 m, and the maximum height of piles is 2.70 m, the maximum number of bags to be stored in two piles, are
  • A.  2500 bags
  • B.  1500 bags
  • C.  2000 bags
  • D.  3000 bags
  • Correct Answer: Option D

Proper batching ensures

Proper batching ensures
  • A.  workability
  • B.  strength
  • C.  durability
  • D.  all
  • Correct Answer: Option D

Specified compressive strengh of concrete is obtained from cube tests at the end of

Specified compressive strengh of concrete is obtained from cube tests at the end of
  • A.  7 days
  • B.  14 days
  • C.  21 days
  • D.  28 days.
  • Correct Answer: Option D

For batching 1:3:6 concrete mix by volume, the ingredients required per bag of 50 kg cement, are:

For batching 1:3:6 concrete mix by volume, the ingredients required per bag of 50 kg cement, are:
  • A.  70 litres of sand and 120 litres of aggregates
  • B.  105 litres of sand and 140 litres of aggregates
  • C.  105 litres of sand and 210 litres of aggregates
  • D.  70 kg of sand and 140 litres of aggregates
  • Correct Answer: Option C

The produce impermeable concrete

The produce impermeable concrete
  • A.  proper compaction of concrete is required
  • B.  all
  • C.  properly graded and non-porous aggregates are requied
  • D.  proper curing of concrete is required
  • Correct Answer: Option B

Grading of sand causes great variation in

Grading of sand causes great variation in
  • A.  workability of concrete
  • B.  strength of concrete
  • C.  durability of concrete
  • D.  all
  • Correct Answer: Option D

Hardening of cement occurs at

Hardening of cement occurs at
  • A.  slow rate during the first few days and afterwards it continues to increase at a rapid rate
  • B.  rapid rate during the first few days and afterwards it continues to increase at a decreased rate
  • C.  none of these.
  • D.  uniform rate throughout its age
  • Correct Answer: Option C

For construction of structures in sea water, the cement generally preferred to, is

For construction of structures in sea water, the cement generally preferred to, is
  • A.  Portland-pozzolana cement
  • B.  quick setting cement
  • C.  low heat Portland cement
  • D.  rapid hardening cement
  • Correct Answer: Option A